A complete switchgear RFQ gives every bidder the same electrical duties, mechanical interfaces, control requirements and delivery boundaries. Without that common basis, quotations can look comparable while including different breakers, protection functions, compartment designs, tests and documentation.
Before contacting switchgear manufacturers, assemble the single-line diagram, rating schedule, feeder list, protection philosophy, layout information and project standards. The RFQ does not need every final relay setting, but it must define enough inputs for a supplier to select a compliant assembly and clearly list assumptions.
Why Incomplete Switchgear RFQs Produce Unreliable Prices
A request for “ten panels of 12 kV switchgear” leaves major cost drivers undefined. One supplier may quote fixed switch-fuse units, another may use withdrawable circuit breakers, and a third may include relays, CTs, internal-arc construction and commissioning. All three prices can be technically different even if the panel count is identical.
A good RFQ links the equipment to the power-system studies and site interfaces. It also requires bidders to separate compliance, deviations, options and exclusions. This turns the quotation into a reviewable technical offer rather than a catalog-based estimate.
RFQ Package Map
| RFQ document | Purpose | Minimum content |
| Single-line diagram | Defines circuits and system architecture | Sources, buses, couplers, transformers, feeders, earthing and metering points |
| Equipment data sheet | Defines assembly ratings and construction | Voltage, current, fault duty, insulation, enclosure and access |
| Feeder schedule | Defines each functional unit | Circuit duty, device, rating, protection, metering and cable interface |
| Protection and control philosophy | Defines how circuits operate and trip | Functions, CT/VT inputs, logic, auxiliary power and communication |
| Layout and interface drawings | Defines physical fit | Room, foundation, cable entry, bus duct, access and transport limits |
| Inspection and test plan | Defines acceptance evidence | Type-test review, routine tests, FAT, witness points and site scope |
| Document schedule | Defines review and handover | Proposal, approval, manufacturing, shipment and as-built documents |
| Commercial scope sheet | Defines supply responsibility | Quantity, delivery, spares, supervision, training, warranty and exclusions |
1. Freeze the Single-Line Diagram and Circuit List
The single-line diagram is the foundation of switchgear design. Give every panel and circuit a unique tag. Show incoming sources, transformers, main buses, bus sections, couplers, outgoing feeders, earthing arrangement, metering points and connections to other packages.
For each functional unit, identify its role: incomer, transformer feeder, motor feeder, capacitor feeder, bus coupler, metering panel, auxiliary supply or spare. State whether the device must switch normal load, interrupt faults, provide isolation or establish an earthed condition.
The drawing should also show all normally open and normally closed points. If a tie breaker can close, the short-circuit study and interlock philosophy must cover that operating mode.
2. Provide Complete Electrical Ratings
Electrical switchgear suppliers need ratings for the assembly and for each installed device. Do not provide only nominal voltage and load current.
| Electrical input | What to state | Why it affects the quotation |
| System voltage | Nominal voltage, highest system voltage and frequency | Defines product class and equipment duty |
| Insulation | Power-frequency and impulse withstand levels | Controls clearances, insulation and tested design |
| Normal current | Main bus, branch bus and feeder continuous currents | Controls conductors, connections and temperature rise |
| Short-circuit duty | Breaking current, making current, short-time current and duration, peak current | Controls breakers, switches, buses and bracing |
| System earthing | Solid, resistance, reactance, isolated or other arrangement | Affects protection, insulation and earthing-switch duties |
| Operating duty | Switching frequency, load type and duty cycle | Affects device class and endurance |
| Future conditions | Planned transformer, generator, motor or source additions | Can change bus current and fault level |
Attach the fault-study results or state the design basis and clearing duration. A breaker interrupting rating is not the same as the assembly short-time withstand rating. If ratings are preliminary, require the bidder to show the values assumed and the price impact of changing them.
3. Define the Switching and Protection Equipment
State whether each circuit uses a circuit breaker, load-break switch, switch-fuse combination, contactor, disconnector or another device. For breakers, define fixed or withdrawable construction, operating mechanism, control voltage, trip and close coils, auxiliary contacts and required operating sequence.
For fuse-based circuits, provide the protected equipment data and coordination requirements. Include fuse holders, striker operation, indication and spare fuse links. For disconnectors and earthing switches, define ratings, position indication, operating method and interlocks.
Withdrawable breaker construction affects panel layout, interlocks, testing and spare-device strategy. Source: L&R Electric.
4. Specify Protection, Metering and Control
List the required protection functions for each circuit, even if final settings will be issued later. Identify relay make or approved functional specification, communication protocol, binary input and output count, event recording, time synchronization and test facilities.
Provide a CT and VT schedule with ratios, cores, accuracy or protection classes, burden, secondary rating and connection. Separate revenue metering, operational metering and protection requirements. State who supplies any utility-approved meters and whether they are installed, wired and tested by the switchgear manufacturer.
Control requirements should cover:
- Local and remote open and close commands.
- Control switches, selector switches, lamps and mimic indication.
- AC and DC auxiliary voltages and permissible variation.
- Trip-circuit supervision, anti-pumping, lockout and close permissives.
- Automatic transfer, bus-coupler and source interlock logic.
- SCADA, DCS, substation automation or building-management interfaces.
- Communication protocols, ports, network media and point list.
If the supplier must program relays, gateways or PLC logic, state whether settings, logic diagrams, source files and configuration backups are contract deliverables.
5. Define Construction and Mechanical Interfaces
The RFQ should identify low- or medium-voltage class, fixed or withdrawable design, air or other insulation arrangement, metal-clad or metal-enclosed construction, bus scheme and required compartmentation. For IEC medium-voltage equipment, state the loss-of-service-continuity category, partition class and internal-arc classification where required.
Provide room and installation constraints:
- Indoor, outdoor, kiosk or prefabricated substation installation.
- Front-only or front-and-rear access.
- Maximum lineup dimensions, section dimensions and transport limits.
- Foundation channels, floor openings, floor loading and anchoring.
- Top or bottom cable entry, cable quantity, conductor size and termination type.
- Bus duct, transformer throat or existing-bus transition interfaces.
- Pressure-relief direction, arc duct and switchroom clearance.
- Space for installed spares, blank panels and future lineup extension.
Compartment and cable-interface details must be defined before the general arrangement is approved. Source: L&R Electric.
State busbar material, current ratings, insulation, joint treatment, neutral arrangement and earth-bar duty. If a preferred component list is mandatory, distinguish required brands from acceptable equivalents and define the approval process for substitutions.
6. State Environmental and Site Conditions
Provide ambient-temperature range, altitude, humidity, condensation, pollution, dust, salt, corrosive gases, solar exposure, rainfall, wind, seismic requirements and hazardous-area conditions where applicable. State enclosure ingress protection and corrosion-protection requirements.
For replacement projects, also provide existing room dimensions, photographs, access route, lifting limits, foundation details, cable lengths and shutdown constraints. A new panel may meet electrical ratings but still fail to fit the existing cables or transport route.
7. Name the Standards and Required Evidence
A phrase such as “comply with international standards” is not sufficient. List the applicable IEC, IEEE, ANSI, UL, GB or utility standards and their required editions. Define which standard governs the complete assembly and which standards apply to breakers, relays, instrument transformers and other major components.
Separate three evidence levels:
- Type-test evidence demonstrates that a representative design passed specified design tests.
- Routine tests are performed on each manufactured assembly as required by the governing standard.
- Factory acceptance testing verifies the project configuration, wiring, logic and documentation before shipment.
Require bidders to identify the design covered by their type-test reports and explain any differences from the offered assembly. For internal-arc claims, include accessibility, tested sides, current, duration and exhaust arrangement. Do not accept “arc resistant” without a defined classification.
8. Build a Project-Specific FAT Plan
The FAT scope should reflect the equipment and project logic. It can include visual and dimensional checks, nameplate verification, mechanical operation, interlocks, wiring continuity, insulation tests, breaker timing or operation, CT/VT ratio and polarity checks, secondary injection, meter checks, alarm and trip simulation, communication tests and source-transfer logic.
State which tests are hold points, witness points or document-review points. Define notice periods, test procedures, acceptance criteria, retest responsibility and whether remote witnessing is acceptable. Also state which tests will be repeated or completed during site acceptance and commissioning.
9. Define the Document Deliverables
| Project stage | Documents to request |
| With quotation | Completed data sheet, compliance schedule, deviations, preliminary GA, SLD, component list, ratings and delivery schedule |
| For approval | GA and foundation drawings, schematics, wiring diagrams, terminal plans, interlock logic, cable data and document index |
| Before FAT | Approved test procedures, relay and meter data, component manuals, type-test references and inspection plan |
| Before shipment | Routine and FAT reports, packing list, shipping dimensions, lifting instructions and storage requirements |
| At handover | As-built drawings, settings and configuration files, operation manual, maintenance schedule, spare-parts list and certificates |
Specify file formats, language, number of hard copies, electronic naming rules and review times. Require a master document register so that missing drawings are visible before shipment.
10. Clarify Supply and Interface Boundaries
State who supplies and installs incoming cables, terminations, bus duct, transformer connections, control cables, DC system, SCADA panels, arc ducts, foundation steel, earthing conductors and auxiliary power. Clarify whether the switchgear supplier provides relay settings, coordination studies, site supervision, commissioning, operator training and energization support.
For package interfaces, identify the responsible party for:
- Transformer trip and alarm signals.
- Generator or utility source synchronizing and transfer logic.
- External CTs, VTs and revenue metering.
- Existing switchgear extensions and bus transitions.
- Communication switches, gateways and fiber accessories.
- Protection settings, SCADA database and end-to-end testing.
Compact switchgear can combine switching, protection, earthing and automation, making scope boundaries especially important. Source: L&R Electric.
11. Make Supplier Quotations Comparable
Issue a bidder response schedule instead of allowing each supplier to choose its own format. Ask every bidder to state:
- Compliance, exception or deviation against every specification clause.
- Guaranteed ratings and the standard used.
- Panel-by-panel equipment list and major component manufacturers.
- Installed spares, blank spaces and future extension provisions separately.
- Included engineering, tests, documents, training and site services.
- Technical assumptions, purchaser inputs and exclusions.
- Manufacturing lead time, drawing schedule and delivery terms.
- Warranty, spare-parts support and recommended maintenance.
Compare the base compliant offer first. Keep optional items such as arc ducts, redundant relays, remote racking, special tests and commissioning support as separate priced lines unless they are mandatory.
Common RFQ Errors
- Sending a panel count without a feeder schedule or circuit duties.
- Providing nominal voltage but no insulation or short-circuit data.
- Requesting “standard protection” without relay functions or CT/VT requirements.
- Leaving cable entry, size and termination responsibility until drawing review.
- Asking for internal-arc construction without class, current, duration or accessible sides.
- Using “spare feeder” without saying whether the breaker and controls are installed.
- Requesting FAT without defining tests, acceptance criteria and witness points.
- Failing to list site supervision, commissioning and training as priced scope items.
Frequently Asked Questions
What is the minimum information for an initial switchgear budget quote?
Provide the single-line diagram, voltage class, bus and feeder currents, short-circuit duty, panel quantity, main device type, indoor or outdoor location, control voltage and required delivery date. Mark all preliminary values and request assumptions.
Should relay settings be finalized before the RFQ?
Not always. Protection functions, CT/VT inputs, trip logic and coordination objectives should be defined. Final settings can follow approved equipment data and the completed protection study if that workflow is stated.
What should be included for a replacement project?
Include existing nameplates, drawings, protection schematics, room and foundation dimensions, cable data, photographs, bus interfaces, shutdown windows and the required sequence for removal and installation.
How should type-test reports be evaluated?
Check the standard, edition, tested ratings and construction against the offered design. Ask the bidder to explain differences in bus rating, compartment arrangement, enclosure, breaker or arc-exhaust system.
What is the difference between a blank panel and an installed spare feeder?
An installed spare normally includes the switching device, bus connection, protection, controls and cable compartment. A blank panel or future space may include only enclosure and expansion provisions. Define each quantity separately.
Should commissioning be part of the manufacturer’s quotation?
Request it as a defined base or optional scope. State duration, location, travel assumptions, tests, tools, reports and responsibility for relay settings and energization support.
How can an EPC team compare offers from different manufacturers?
Use a common data sheet, feeder schedule, compliance matrix, component schedule, test list and commercial scope table. Normalize deviations and exclusions before comparing price.
Send a Reviewable RFQ, Not Just a Panel List
A precise RFQ allows a switchgear manufacturer to quote the correct electrical duty, construction and project services without hiding assumptions in the price. Prepare the one-line diagram, ratings, protection philosophy, mechanical interfaces, environmental data, standards, tests and deliverables before bid issue. Contact L&R Electric with the RFQ package to review the configuration and request a project quotation.